Highgate Business Park

Highgate Business Park 2017-05-24T09:30:49+00:00

Project Description

Previous design work carried out for this project resulted in an earthworks imbalance of 200,000m3 that the existing consultants were struggling to resolve. Candor3 were asked to review work to date and determine if a solution were available.

The commercial component of the project was quickly resolved and a consent lodged to allow earthworks to proceed in November 2016. The residential component of the project was however a geotechnically challenging piece of land and the scheme derived was fighting the landform and preventing an earthworks balance.

Through a rescheming of the residential component of the land an earthworks balance was achieved with lower geotechnical stabilization costs and a slight increase in the developable area. Earthworks are underway on the commercial component of the development and with the Resource Consent having issued civil works should commence in early 2017.

 

Similar Projects

2017-05-24T09:30:49+00:00

Highgate Business Park

,

Previous design work carried out for this project resulted in an earthworks imbalance of 200,000m3 that the existing consultants were struggling to resolve. Candor3 were asked to review work to date and determine if a solution were available. The commercial component of the project was quickly resolved and a consent lodged to allow earthworks to [...]

2017-05-24T09:31:25+00:00

Hobsonville Workspace, Hobsonville

,

This small 14 unit commercial development was consented in April 2016 with construction commencing shortly thereafter. Works to provide infrastructure and access to facilitate building works are now complete with building to commence in 2017. Candor³ have carried out the engineering design and observation works as well as dealing with all survey matters pertaining to [...]

2017-05-24T09:32:21+00:00

79 Ormiston Rd, Flat Bush

,

Construction of this 15.0ha business park in East Tamaki commenced in early 2016 and civil works for the initial stage of the project are nearing completion. Candor³ have carried out all of the engineering design, management and survey for the project to date. Further development will occur on completion of the first stage infrastructure. [...]